The Downtown Infrastructure project is to accommodate the anticipated redevelopment of the downtown area and bring the aging water (potable and non-potable), storm drain and sewer facilities up to current standards. For the purpose of this project, the downtown area is bounded by the following streets; Brentwood Boulevard, Pine Street, Third Street and Birch Street including the following alleys; Diablo Way, Midway and Park Way.

The project includes the installation of new water, storm drain and sewer facilities, the rehabilitation of existing facilities and either the removal of, or the replacement of, existing infrastructure to accommodate future redevelopment.

Downtown Infrastructure - Phase I was completed in December 2008 and consisted of the following utility work to accommodate the new Civic Center related projects:

a) A new 16”/12” potable water line on Maple Street.
b) Install fiber optic conduit links on Maple Street.
c) A new 6” non-potable water line on Oak Street.
d) A new 18” storm drain and 10” sanitary sewer on Third Street.

Downtown Infrastructure - Phase II which is currently under design will complement the Downtown Streetscape and consists of the following street and utility work:

a) Roadway design for Oak Street from Brentwood Boulevard to Third Street; First Street from Maple Street to Chestnut Street; Chestnut Street from Brentwood Boulevard to Third Street; Brentwood Boulevard from Maple Street to Chestnut Street; Second Street from Brentwood Boulevard to Oak Street; Park Way from Oak Street to Chestnut Street; Midway from Maple Street to Chestnut Street and Diablo Way from Maple Street to Chestnut Street.
b) 8” sewer main design on Chestnut Street from Third Street to Diablo Way; Diablo Way, Midway and Park Way from Oak Street to Chestnut Street.
c) Potable water main design for Diablo Way from west of Oak Street to east of chestnut Street; Midway from Maple Street to Chestnut Street and Park Way from Oak Street to east of Chestnut Street.
d) Electrical, telephone and irrigation design, as necessitated by the above downtown infrastructure and streetscape work.
Construction for Downtown Infrastructure - Phase II is scheduled to start in October 2010 and is anticipated to take approximately 12 months.

Downtown Infrastructure - Phase III which constitutes the remaining areas will be completed at a future date.

The Downtown Infrastructure Project is funded by a combination of the various facility fee and redevelopment agency funds.