CITY COUNCIL AGENDA ITEM NO. 4

Meeting Date: December 12, 2006

Subject/Title: Adopt a Resolution accepting the work performed by Talus Construction, Inc., for Sarah Street Water Distribution System Improvements, CIP Project No. 562-56350, and directing the City Clerk to file a Notice of Completion with the County Recorder.

Prepared by: Chris Ehlers, Deputy Director of Public Works

Submitted by: Bailey Grewal, Director of Public Works/City Engineer

RECOMMENDATION
Adopt a Resolution accepting the work performed by Talus Construction, Inc., for Sarah Street Water Distribution System Improvements, CIP Project No. 562-56350, and directing the City Clerk to file a Notice of Completion with the County Recorder.

PREVIOUS ACTION
On May 23, 2006, by Resolution No. 2006-113, City Council awarded the construction contract for Sarah Street Water Distribution System Improvements, CIP Project No. 562-56350 to Talus Construction, Inc.

BACKGROUND
The scope of the original project was to replace only the 8-inch water line. In an effort to minimize the residential inconvenience and traffic impacts caused by the nature of this project; the Wastewater Division was contacted to conduct an inspection of the collection system on Sarah Street. Staff found numerous low spots and degradation of the existing 8-inch sewer main by televising the line. Staff was unable to televise the entire sewer main due to tight bends and a reduction in pipe size. Staff concluded it was more economical to replace both the 8-inch water line and the 8-inch sewer line simultaneously.

The City of Brentwood originally advertised the project for public bid beginning May 27, 2005 with the bid opening on June 16, 2005. Due to the lowest bidder’s failure to provide the required bond and insurance documents within the time period required by the bid documents, staff re-bid the project.

Staff again advertised the project for construction on March 6, 2006 and bids were opened on April 21, 2006. A total of three (3) bids were received. The bids were reviewed and the lowest responsive, responsible bid was received from Talus Construction, Inc.

Talus Construction, Inc. has now completed the work consisting of replacement of an 8-inch domestic water line and an 8-inch sanitary sewer line along Sarah Street between Dainty Avenue and Summer Circle. Talus Construction, Inc. completed the work on-time, under budget and to the satisfaction of the City. Their crew was professional, extremely competent, and they worked hard to minimize the inconvenience to the residents in that area. City staff received compliments from a few residents who were pleased with the crew and their cooperative nature.

FISCAL IMPACT
The total contract amount for the work performed by Talus Construction, Inc. for the Sarah Street Water Distribution System Improvements, CIP 562-56350, is as follows:

Contractor Actual Amount City Council Approved Amount
Talus Construction, Inc. $253,445.37 $262,600.80

The work is complete and is under City Council approved amounts for these improvements.

Attachments:
• Resolution
• Notice of Completion

RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRENTWOOD ACCEPTING THE WORK PERFORMED BY TALUS CONSTRUCTION INC., FOR SARAH STREET WATER DISTRIBUTION SYSTEM IMPROVEMENTS, CIP PROJECT NO. 562-56350, AND DIRECTING THE CITY CLERK TO FILE A NOTICE OF COMPLETION WITH THE COUNTY RECORDER.

WHEREAS, the scope of the original project was to replace only the 8-inch water line; and

WHEREAS, staff concluded it was more economical to replace both the 8-inch water line and the 8-inch sewer line simultaneously; and

WHEREAS, on May 23, 2006, by Resolution No. 2006-113, City Council awarded the construction contract for Sarah Street Water Distribution System Improvements, CIP Project No. 562-56350 to Talus Construction, Inc; and

WHEREAS, Talus Construction, Inc. has completed the work consisting of replacement of an 8-inch domestic water line and an 8-inch sanitary sewer line along Sarah Street between Dainty Avenue and Summer Circle; and

WHEREAS, Talus Construction, Inc. completed the work on-time, under budget and to the satisfaction of the City.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Brentwood does hereby accept the work performed by Talus Construction, Inc., for Sarah Street Water Distribution System Improvements, CIP Project No. 562-56350, and the City Clerk is directed to file a Notice of Completion with the County Recorder.

PASSED, APPROVED AND ADOPTED by the City Council of the City of Brentwood at a regular meeting on the 12th day of December 2006 by the following vote:

RECORDING REQUESTED BY
CITY OF BRENTWOOD

WHEN RECORDED RETURN TO:
CITY CLERK
CITY OF BRENTWOOD
150 City Park Way
BRENTWOOD, CA 94513

NOTICE OF COMPLETION

NOTICE IS HEREBY GIVEN THAT:

THE CITY OF BRENTWOOD, a general law city, in the County of Contra Costa, State of California, did, on the 23rd day of May 2006, enter into an agreement with Talus Construction, Inc., for Sarah Street Water Distribution System Improvements, CIP Project No. 562-56350.

The work described in the contract documents was to furnish all material, labor, and equipment necessary to complete said work for Sarah Street Water Distribution System Improvements, located at Sarah Street, between Dainty Avenue and Summer Circle in Brentwood, California.

On the 12th day of December 2006, said contract, as a whole was completed and the work was accepted by the City Council of the City of Brentwood.

I hereby certify under penalty of perjury that the facts set forth in the foregoing Notice of Completion are true and correct.

Executed at Brentwood, Contra Costa County, State of California, on December 12, 2006.

By: __________________________
Margaret Wimberly, CMC, City Clerk
City of Brentwood, California
 

City Administration