CITY COUNCIL AGENDA ITEM NO. 16

Meeting Date: December 13, 2005

Subject/Title: Adopt a Resolution approving and authorizing the City Manager to execute Contract Term and Amount Amendments for certain Professional Services Agreements.

Prepared by: Engineering: L. Sanders, Project Services Specialist

Submitted by: Engineering: B. Grewal, City Engineer

RECOMMENDATION
Adopt a Resolution approving and authorizing the City Manager to execute the following Contract Term Amendments for time extensions and amount amendments for Professional Services Agreements (Exhibit “A” attached) as needed for various project completions: Amendment Four with Bellecci & Associates, Inc. for the Lone Tree Way Widening; Amendment Four with Gray Bowen and Company for the Lone Tree Way Widening; Amendment One with Biggs Cardosa Associates, Inc. for the Communication Tower (Police Station); Amendment One with BKF Engineers for the Sarah Street Water Distribution System Improvements; Amendment One with Control Manufacturing, Inc. for the Water Distribution Telemetry/SCADA; Amendment One with JSP Automation for the Wastewater Treatment Plant; Amendment Two with Kimley Horn & Associates for the Zone 1 Reservoir 1.3; Amendment Two with The Covello Group for the Zone 1 Reservoir 1.3; Amendment Two with Luhdorff & Scalmanini Consulting Engineers for the Water Well #15; Amendment One with Mark Thomas & Company for the Empire Avenue Expansion – North; Amendment One with Milani & Associates for the Grant Street School Infrastructure; Amendment Three with The Covello Group for the Sunset Industrial Complex; Amendment Two with RGM and Associates for the New Police Station, which includes a contract increase of $18,000; Amendment One with Transcomp Systems for the Tower Software Package, which includes a contract increase of $35,000; Amendment One with Sweetser and Associates for the Solid Waste Transfer Station.

PREVIOUS ACTION
City Council authorized staff to execute several contracts for various projects as shown in Exhibit “A”.

BACKGROUND
As a streamlining process, staff reviews various professional service agreements at the end of every year and brings them forward to the City Council for appropriate time extensions. As you may know, several Capital Improvement Projects are in various stages of design and construction. Many of the projects are in the final stage of completion with minor punchlist items to be finished and as-built drawings to be submitted. Staff has prepared a status of projects (Exhibit “A” attached) that identify the phase of each of the projects which require a Contract Amendment to allow for design and or construction completion. Typically, a design professional may start a project during the preliminary design phase and continue through final design and construction phases of the project, until the final as-built drawing stage of the project. The "project process" in California, in dealing with any environmental issues or outer agency issues, increased design and construction time by elevating this work to labor-intensive procedures. These procedures increase the timeframe in which we can expect to complete a design or construction on any given project.

FISCAL IMPACT
Thirteen of the fifteen contract amendments do not have any affect on the fiscal impact of the associated projects. RGM and Associates’ contract amendment includes a change order of $18,000, which will be funded through the New Police Station budget for additional contract close out and on-call warranty services work. This change order brings the total of their contract to $493,000. Transcomp Systems has an increase of $35,000 for additional conversion services, bringing the total of their contract to $83,145. There are funds available in the Solid Waste Operation’s general budget to cover this contract increase.

Attachments:
Resolution
Exhibit “A”
Contract Amendments

RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRENTWOOD APPROVING AND AUTHORIZING THE CITY MANAGER TO EXECUTE THE FOLLOWING CONTRACT TERM AMENDMENTS FOR TIME EXTENSIONS AND AMOUNT AMENDMENTS FOR PROFESSIONAL SERVICES AGREEMENTS AS NEEDED FOR VARIOUS PROJECT COMPLETIONS: AMENDMENT FOUR WITH BELLECCI & ASSOCIATES, INC. FOR THE LONE TREE WAY WIDENING; AMENDMENT FOUR WITH GRAY BOWEN AND COMPANY FOR THE LONE TREE WAY WIDENING; AMENDMENT ONE WITH BIGGS CARDOSA ASSOCIATES, INC. FOR THE COMMUNICATION TOWER (POLICE STATION); AMENDMENT ONE WITH BKF ENGINEERS FOR THE SARAH STREET WATER DISTRIBUTION SYSTEM IMPROVEMENTS; AMENDMENT ONE WITH CONTROL MANUFACTURING, INC. FOR THE WATER DISTRIBUTION TELEMETRY/SCADA; AMENDMENT ONE WITH JSP AUTOMATION FOR THE WASTEWATER TREATMENT PLANT; AMENDMENT TWO WITH KIMLEY HORN & ASSOCIATES FOR THE ZONE 1 RESERVOIR 1.3; AMENDMENT TWO WITH THE COVELLO GROUP FOR THE ZONE 1 RESERVOIR 1.3; AMENDMENT TWO WITH LUHDORFF & SCALMANINI CONSULTING ENGINEERS FOR THE WATER WELL #15; AMENDMENT ONE WITH MARK THOMAS & COMPANY FOR THE EMPIRE AVENUE EXPANSION – NORTH; AMENDMENT ONE WITH MILANI & ASSOCIATES FOR THE GRANT STREET SCHOOL INFRASTRUCTURE; AMENDMENT THREE WITH THE COVELLO GROUP FOR THE SUNSET INDUSTRIAL COMPLEX; AMENDMENT TWO WITH RGM AND ASSOCIATES FOR THE NEW POLICE STATION, WHICH INCLUDES A CONTRACT INCREASE OF $18,000; AMENDMENT ONE WITH TRANSCOMP SYSTEMS FOR THE TOWER SOFTWARE PACKAGE, WHICH INCLUDES A CONTRACT INCREASE OF $35,000; AMENDMENT ONE WITH SWEETSER AND ASSOCIATES FOR THE SOLID WASTE TRANSFER STATION.

WHEREAS, City Council authorized staff to execute contracts and work toward completion of several public works and master plan projects; and

WHEREAS, contract modifications are required in order to continue with the necessary work.

NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Brentwood, does hereby approve and authorize the City Manager to execute the following Contract Term Amendments and Amount Amendments of Professional Services Agreements, also summarized in Exhibit “A” attached.
1. Amendment Four with Bellecci & Associates, Inc. for the Lone Tree Way Widening;
2. Amendment Four with Gray Bowen and Company for the Lone Tree Way Widening;
3. Amendment One with Biggs Cardosa Associates, Inc. for the Communication Tower (Police Station);
4. Amendment One with BKF Engineers for the Sarah Street Water Distribution System Improvements;
5. Amendment One with Control Manufacturing, Inc. for the Water Distribution Telemetry/SCADA;
6. Amendment One with JSP Automation for the Wastewater Treatment Plant;
7. Amendment Two with Kimley Horn & Associates for the Zone 1 Reservoir 1.3;
8. Amendment Two with The Covello Group for the Zone 1 Reservoir 1.3;
9. Amendment Two with Luhdorff & Scalmanini Consulting Engineers for the Water Well #15;
10. Amendment One with Mark Thomas & Company for the Empire Avenue Expansion – North;
11. Amendment One with Milani & Associates for the Grant Street School Infrastructure;
12. Amendment Three with The Covello Group for the Sunset Industrial Complex;
13. Amendment Two with RGM and Associates for the New Police Station, which includes a contract increase of $18,000;
14. Amendment One with Transcomp Systems for the Tower Software Package, which includes a contract increase of $35,000;
15. Amendment One with Sweetser and Associates for the Solid Waste Transfer Station.

PASSED, APPROVED AND ADOPTED by the City Council of the City of Brentwood at a regular meeting on the 13th day of December 2005 by the following vote:

Exhibit "A" - Project Status
Project Name Project No.
Project Mgr. Consultants Phase of Project Expiration Date
Lone Tree Way Widening 336-3131
B. Bornstein Bellecci & Associates, Inc.
Gray Bowen and Company Preliminary design and environmental work. Project
Completion
Communication Tower (Police Station) 337-3708
G. Leech Biggs Cardosa Associates, Inc. Finalizing design and moving into bidding phase. Spring 2006 for construction. Project
Completion
Sarah Street Water Distribution System Improvements 562-5635
C. Ehlers BKF Engineers Contractor has not started work. Project may need to be re-bid. Project
Completion
Water Distribution Telemetry/SCADA 562-5620
562-5624
P. Eldredge Control Manufacturing, Inc. 95% complete. Working on functional testing and training. Project
Completion
Wastewater Treatment Plant 592-5911
P. Eldredge JSP Automation Completing identified punch list items. Project
Completion
Zone 1 Reservoir 1.3 562-5630
P. Eldredge Kimley Horn & Associates
The Covello Group 90% complete. Need PG&E power and prepare punch list. Project
Completion
Water Well #15 562-5631
P. Eldredge Luhdorff & Scalmanini Consulting Engineers Well work is complete. Starting the design of sitework. Project
Completion
Empire Avenue Expansion - North 336-3151
P. Eldredge Mark Thomas & Company Work almost complete. Reimbursement Agreement going to December 13th Council Meeting. Project
Completion
Grant Street School Infrastructure 336-3146
B. Bornstein Milani & Associates 85% complete. Intersection work needed at Grant Street / Lone Oak and signal work at Adams / Grant Street. Misc. landscape/trail improvements. Project
Completion
Sunset Industrial Complex 336-3128
P. Eldredge The Covello Group Construction of IPARQ Way scheduled for completion February 2006. Project
Completion
New Police Station 337-3142
M. Huber RGM and Associates Contract close out and warranty period. Project Completion
Tower Software Package J. Carlson Transcomp Systems Data conversion complete, clean up of data required. Currently customizing reports and software. Project
Completion
Solid Waste Transfer Station 542-5402
J. Carlson Sweetser and Associates Preliminary permit work is complete. Once construction documents are ready, additional permits will be needed. Project Completion

AMENDMENT FOUR TO AGREEMENT FOR PROFESSIONAL SERVICES OF BELLECCI & ASSOCIATES, INC.

LONE TREE WAY WIDENING
CIP PROJECT NO. 336-3131

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Bellecci & Associates, Inc.

WHEREAS, on June 26, 2001, the City of Brentwood entered into a contract with Bellecci & Associates to obtain specific skills and technical expertise in the design preparation of the Lone Tree Way Widening, CIP Project No. 336-3131 (the Contract).

WHEREAS, on June 25, 2002, the contract term was amended to reflect contract completion of December 31, 2003.

WHEREAS, on December 9, 2003, the contract term was amended to reflect contract completion of December 31, 2004.

WHEREAS, on December 14, 2004, the contract term was amended to reflect contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Bellecci & Associates

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT FOUR TO AGREEMENT FOR PROFESSIONAL SERVICES OF GRAY BOWEN AND COMPANY

LONE TREE WAY WIDENING
CIP PROJECT NO. 336-3131

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Gray Bowen and Company.

WHEREAS, on June 26, 2001, the City of Brentwood entered into a contract to obtain specific skills and technical expertise in the preparation of a Project Study Report (PSR) for the Lone Tree Way Widening Project, CIP Project No. 336-3131 (the Contract).

WHEREAS, on June 25, 2002 the City of Brentwood extended the contract termination date to December 31, 2003.

WHEREAS, on December 9, 2003, the City of Brentwood extended the contract termination date to December 31, 2004.

WHEREAS, on December 14, 2004, the contract term was amended to reflect contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Gray Bowen and Company

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk
 

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF BIGGS CARDOSA ASSOCIATES, INC.

COMMUNICATION TOWER
CIP PROJECT NO. 337-3708

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Biggs Cardosa Associates, Inc.

WHEREAS, on January 21, 2005, the City of Brentwood entered into a contract with Biggs Cardosa Associates, Inc. to obtain structural engineering services for the Communication Tower, CIP Project No. 337-3708 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Biggs Cardosa Associates, Inc.

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF BKF ENGINEERS SURVEYORS PLANNERS

SARAH STREET WATER DISTRIBUTION SYSTEM IMPROVEMENTS
CIP PROJECT NO. 562-5635

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and BKF Engineers Surveyors Planners.

WHEREAS, on December 20, 2004, the City of Brentwood entered into a contract with BKF Engineers Surveyors Planners to obtain professional design services for the Sarah Street Water Distribution System Improvements, CIP Project No. 562-5635 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

BKF Engineers Surveyors Planners

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF CONTROL MANUFACTURING, INC.

WATER DISTRIBUTION TELEMETRY/SCADA
CIP PROJECT NO.’S 562-5620 and 562-5624

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Control Manufacturing, Inc.

WHEREAS, on January 13, 2004, the City of Brentwood entered into a contract with Control Manufacturing, Inc. to obtain professional programming services for the Water Distribution Telemetry/SCADA System, CIP Project No. 562-5620 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Control Manufacturing, Inc.

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF JSP AUTOMATION

WASTEWATER TREATMENT PLANT
PROJECT NO. 592-5911

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and JSP Automation.

WHEREAS, on November 22, 2004, the City of Brentwood entered into a contract with JSP Automation to obtain programming services for the Wastewater Treatment Plant, CIP Project 592-5911 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

JSP Automation

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT TWO TO AGREEMENT FOR PROFESSIONAL SERVICES OF KIMLEY HORN & ASSOCIATES

ZONE 1 RESERVOIR 1.3
PROJECT NO. 562-5630

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Kimley Horn & Associates.

WHEREAS, on August 12, 2003, the City of Brentwood entered into a contract with Kimley Horn & Associates to obtain professional engineering design services for the Zone 1 Reservoir 1.3, CIP Project No. 562-5630 (the Contract).

WHEREAS, on September 14, 2004, the contract term was amended to reflect a contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Kimley Horn & Associates

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT TWO TO AGREEMENT FOR PROFESSIONAL SERVICES OF THE COVELLO GROUP

ZONE 1 RESERVOIR 1.3
PROJECT NO. 562-5630

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and The Covello Group.

WHEREAS, on October 14, 2003, the City of Brentwood entered into a contract with The Covello Group to obtain project management assistance during the planning, design, bidding and construction of the Zone 1 Reservoir 1.3, CIP Project No. 562-5630 (the Contract).

WHEREAS, on December 14, 2004, the contract term was amended to reflect contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

The Covello Group

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT TWO TO AGREEMENT FOR PROFESSIONAL SERVICES OF LUHDORFF & SCALMANINI CONSULTING ENGINEERS

WATER WELL #15
CIP PROJECT NO. 562-5631

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Luhdorff & Scalmanini Consulting Engineers.

WHEREAS, on October 14, 2003, the City of Brentwood entered into a contract with Luhdorff & Scalmanini Consulting Engineers to obtain exploratory test hole drilling, well monitoring, site evaluation and pre-design reports for Water Well #15, CIP Project No. 562-5631 (the Contract).

WHEREAS, on December 14, 2004, the contract term was amended to reflect contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Luhdorff & Scalmanini Consulting Engineers

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF MARK THOMAS & COMPANY

EMPIRE AVENUE EXPANSION – NORTH
CIP PROJECT NO. 336-3151

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Mark Thomas & Company.

WHEREAS, on June 18, 2004, the City of Brentwood entered into a contract with Mark Thomas & Company to obtain design services for improvements to the east side of Empire Avenue, north of Lone Tree Way, CIP Project No. 336-3151 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Mark Thomas & Company

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF MILANI & ASSOCIATES

GRANT STREET SCHOOL INFRASTRUCTURE
CIP PROJECT NO. 336-3146

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Milani & Associates.

WHEREAS, on January 13, 2004, the City of Brentwood entered into a contract with Milani & Associates to obtain design services for Grant Street extension, Anderson Lane and O’Hara extension for the Grant Street School Infrastructure, CIP Project No. 336-3146 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4 of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Milani & Associates

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT THREE TO AGREEMENT FOR PROFESSIONAL SERVICES OF THE COVELLO GROUP

SUNSET INDUSTRIAL COMPLEX
CIP PROJECT NO. 336-3128

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and The Covello Group.

WHEREAS, on June 25, 2002, the City of Brentwood entered into a contract with The Covello Group to obtain construction management services for the Sunset Industrial Complex, CIP Project No. 336-3128 (the Contract).

WHEREAS, on December 9, 2003, the contract term was amended to reflect contract completion of December 31, 2004.

WHEREAS, on December 14, 2004, the contract term was amended to reflect contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

The Covello Group

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT TWO TO AGREEMENT FOR PROFESSIONAL SERVICES OF RGM AND ASSOCIATES

NEW POLICE STATION
CIP PROJECT NO. 337-3142

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and RGM and Associates.

WHEREAS, on September 23, 2003, the City of Brentwood entered into a contract agreement with RGM and Associates for professional Construction Management Services for the New Police Station, CIP Project No. 337-3142 (the Contract).

WHEREAS, on December 14, 2004, the contract term was amended to reflect contract completion of December 31, 2005.

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 1, of the Contract, entitled Scope of Services is amended to include additional contract close out and on-call warranty services work.
2. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
3. Section 5, of the Contract, entitled Payment is amended to increase the contract amount fro $475,000 to $493,000, reflecting an increase of $18,000.
4. All other terms remain unchanged.

RGM and Associates

By______________________________________ Dated: _____________________

_________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF TRANSCOMP SYSTEMS

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Transcomp Systems.

WHEREAS, on February 14, 2005, the City of Brentwood entered into a contract with Transcomp Systems to obtain the Tower Software Package and provide installation and training (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 1, of the Contract, entitled Scope of Services is amended to include additional data conversion services.
2. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
3. Section 5, of the Contract, entitled Payment is amended to increase the contract amount from $48,125 to $83,125, an increase of $35,000.
4. All other terms remain unchanged.

Transcomp Systems

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

AMENDMENT ONE TO AGREEMENT FOR PROFESSIONAL SERVICES OF SWEETSER & ASSOCIATES

SOLID WASTE TRANSFER STATION
CIP PROJECT NO. 542-5402

This Amendment is entered into on December 13, 2005 by and between the City of Brentwood and Sweetser & Associates.

WHEREAS, on July 1, 2004, the City of Brentwood entered into a contract with Sweetser & Associates to obtain solid waste permit and compliance services on an as-needed basis for the Solid Waste Transfer Station, CIP Project No. 542-5402 (the Contract).

NOW, THEREFORE, IT IS AGREED as follows:

1. Section 4, of the Contract, entitled Term is amended to change the termination date to project completion.
2. All other terms remain unchanged.

Sweetser & Associates

By_______________________________________ Dated: _____________________

__________________________________________ ____________________________
Print Name Title

City of Brentwood

By Dated:
Donna Landeros, City Manager

Attest:

By Dated:
Margaret Wimberly, CMC, City Clerk

City Administration
City of Brentwood City Council
150 City Park Way
Brentwood, CA 94513
(925) 516-5440
Fax (925) 516-5441
E-mail allcouncil@brentwoodca.gov