CITY COUNCIL AGENDA ITEM NO. 19

Meeting Date: July 12, 2005

Subject/Title: Update on developer progress at Deer Ridge Subdivision

Prepared by: Randy Kidwell, Chief Building Official

Submitted by: Howard Sword, Director, Community Development Department

RECOMMENDATION
No recommendation at this time.

PREVIOUS ACTION
Direct Staff to:
• Resume issuing new home permits to the Deer Ridge Home Builders by authorizing 106 permits to be issued immediately.

• Authorize staff to enter into a letter agreement with the remaining Home Builders, KB Homes and D.R. Horton Home Builders, guaranteeing completion of the remaining infrastructure improvements, secured by withholding the final 100 permits; 50 from each developer.

• Return to Council on a monthly basis with a progress report and possibly authorizing additional permit releases.

BACKGROUND
Credible progress has been made at the Deer Ridge Subdivision.

• Spyglass is complete and open for traffic.

• Landscaping at the corner of Foothill and Balfour is complete.

• Plans for the Foothill extension and the John Muir Parkway extension have been prepared by Bellecci and Associates and are with the Engineering Department.

• Don Burton Construction Management has begun to enter into contract with contractors to complete the subdivision improvement punch lists. Some critical improvements have been completed, such as getting power to and bringing on-line the irrigation controller servicing the southeast portion of the project and the weed abatement.

• The Zone 3 Pump Station is complete and on-line.

• Final bridge railing and vehicle barrier designs have been submitted to Engineering for plan review.

• Tank and pump station road has been designed and land acquisitions are in progress.

• Ventura and Concord 66” storm drain and road improvement completed.

• Water tank landscaping design concept has been submitted to Engineering for review.

Staff continues to meet weekly with all the participants to insure that the process is on track and that details are not overlooked.

FISCAL IMPACT
We are presently meeting our facility fee cash flow projections.