CITY COUNCIL AGENDA ITEM NO. 12

Meeting Date: April 10, 2001

Subject/Title: Services During Construction for the Zone II 2mg Reservoir – Phase II 
(CIP Project No. 562-5627)

Submitted by: Engineering: J. Stevenson/P. Eldredge

Approved by: Jon Elam, City Manager

RECOMMENDATION
Approve an agreement for services during construction for the Zone II 2mg Reservoir – Phase II, CIP Project No. 562-5627, to PSOMAS and Associates and authorize the City Manager to execute the agreement and necessary documents in the amount of $62,904.00 and grant the City Manager authority to execute change orders up to 10% of the contract amount.

PREVIOUS ACTION
On November 14, 1995 the City Council approved a consulting services agreement with PSOMAS and Associates for the design of the Zone II Reservoir, pump station and corresponding pipelines.

On July 9, 1996 the City Council awarded the construction contract to Ross F. Carrol, Inc., for the construction of the Zone II Reservoir project, CIP 562-5608. This work was subsequently completed and accepted by City Council October 28, 1997.

On September 14, 1999 the City Council approved a consulting services agreement with PSOMAS and Associates for the design of the Zone II 2mg Reservoir – Phase II improvements.

BACKGROUND
The first Zone II Reservoir, pump station and corresponding pipelines were completed in late 1997. As a part of this project, provisions were made for the construction of a second 2 million gallon steel reservoir when growth in that water zone dictated. Currently there is a sufficient population in this water zone to mandate the construction of this reservoir.

The construction consists of piping, grading and concrete work for the foundation, welding of the steel reservoir plates, electrical, and coating of the interior and exterior of the tank. The majority of the required inspections will be performed by City Staff. However, portions of the construction such as the welding, coatings and electrical installation require additional inspections by certified individuals. This contract will provide the required individuals to assist City staff to ensure a successful completion of this project.

The Fiscal Year (FY) 00/01 budget contains funds for the construction of the Zone II 2mg Reservoir – Phase II, CIP Project No. 562-5627, in the amount of $259,000 and Fiscal Year 01/02 includes $1,200,000 for this construction as well. This project’s construction duration will span both Fiscal Years and will be utilizing funds from both. The entire amount for construction is from facility fees paid by development.

Attachment:
Site Map

Top of Page

[City Council]  [City Departments]  [City Forms]  [Boards/Commissions] [Passports] [Search] [FAQ]
[Municipal Code] [What's New]  [Employment]  [Links]  [General Information] [Table of Contents]