CITY COUNCIL AGENDA ITEM NO. 16

Meeting Date: December 12, 2000

Subject/Title: A Resolution to amend Sunset Park Master Plan and Expansion Project, CIP Project #522-5201, to finance the project from Quimby Fees.

Submitted by: Craig D. Bronzan, Director of Parks and Recreation

Approved by: Jon Elam, City Manager

RECOMMENDATION 

Approve resolution to amend Sunset Park Master Plan and Expansion Project, CIP Project #522-5201, to finance the project from Quimby Fees.

PREVIOUS ACTION 

City Council considered a revision in developer fees at their November 28, 2000 City Council meeting. As the park development fees had not been reviewed by the Park and Recreation Commission, Council directed staff to review the proposed park development fees with the Park and Recreation Commission at the November 30, 2000 commission meeting.

BACKGROUND 

At the November 30, 2000 Park and Recreation Commission meeting, the commission reviewed the proposed Park Development Fees that had been considered by City Council on November 28, 2000. In reviewing the proposed fees and approved 2000/2005 CIP program for Parks and Trail Improvements, the commission is recommending that Sunset Park Master Plan and Expansion (CIP Project #522-5201) be moved from "unfunded" to "funded" in the amount of $2,020,000. Staff is requesting City Council approve the commission recommendation.

Once City Council approves this action to move Sunset Park from unfunded to funded, staff will move forward with a meeting with the development community to review the fees. Staff would then bring back a resolution to adjust park development fees to City Council in January 2001.

If approved, the funding of Sunset Park would raise park development fees approximately $1,300 per single-family unit. The total park fee would increase from $5,706 to approximately $7,022.

Attachment: Resolution

RESOLUTION NO.

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BRENTWOOD AMMENDING SUNSET PARK MASTER PLAN AND EXPANSION PROJECT, CIP PROJECT #522-5201, TO FINANCE THE PROJECT FROM QUIMBY FEES.


WHEREAS, on November 28, 2000, the City of Brentwood City Council directed the Park and Recreation Commission to review the proposed park development fee recommendation, and

WHEREAS, on November 30, 2000, the City of Brentwood Park and Recreation Commission reviewed the proposed park development fee recommendation, and

WHEREAS, the Park and Recreation Commission is recommending that City Council amend Sunset Park Master Plan and Expansion Project, CIP Project #522-5201, from "unfunded" to "funded"

NOW, THEREFORE BE IT RESOLVED the City Council of the City of Brentwood approves a resolution amending Sunset Park Master Plan and Expansion Project, CIP Project #522-5201, to finance the project from Quimby fees.

PASSED, APPROVED AND ADOPTED by the City Council of the City of Brentwood at a regular meeting held on December 12, 2000 by the following vote: